August 9, 2023 Zendo KernHawaii County Planning Department101 Pauahi Street, Ste. 3Hilo, HI 96720 SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES Dear Mr. Kern: Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV)hereby submits the Weekly Status Report for the week ending August 6, 2023. Power plantPlant in service. Wellfield KS-22, continued developing the well. If you have any questions, please do not hesitate to… Read More »Weekly Updates – August 9, 2023

weekly update

Weekly Updates – July 31, 2023

  • by

July 31, 2023 Zendo KernHawaii County Planning Department101 Pauahi Street, Ste. 3Hilo, HI 96720 SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES Dear Mr. Kern: Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV)hereby submits the Weekly Status Report for the week ending July 30, 2023. Power plantPlant in service. Wellfield KS-22, continued developing the well. If you have any questions, please do not hesitate to… Read More »Weekly Updates – July 31, 2023

weekly update

Weekly Updates – July 24, 2023

  • by

July 24, 2023 Zendo KernHawaii County Planning Department101 Pauahi Street, Ste. 3Hilo, HI 96720 SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES Dear Mr. Kern: Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV)hereby submits the Weekly Status Report for the week ending July 23, 2023. Power plantPlant in service. Wellfield KS-22, tagged new target zone at 5,875’, currently developing the well. If you have any… Read More »Weekly Updates – July 24, 2023

weekly update

Weekly Updates – July 17, 2023

  • by

July 17, 2023 Zendo KernHawaii County Planning Department101 Pauahi Street, Ste. 3Hilo, HI 96720 SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES Dear Mr. Kern: Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV)hereby submits the Weekly Status Report for the week ending July 16, 2023. Power plantPlant in service. Wellfield KS-22, continued drilling to new target, current depth is 5890’. If you have any questions,… Read More »Weekly Updates – July 17, 2023

weekly update

Weekly Updates – July 10, 2023

  • by

July 10, 2023 Zendo KernHawaii County Planning Department101 Pauahi Street, Ste. 3Hilo, HI 96720 SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES Dear Mr. Kern: Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV)hereby submits the Weekly Status Report for the week ending July 9, 2023. Power plantPlant in service. Wellfield KS-22, abandoned original target, cement plugged to 4115’, commenced DLNR approved sidetrack at 4140’ to… Read More »Weekly Updates – July 10, 2023

weekly update

Weekly Updates – July 3, 2023

  • by

July 3, 2023 Zendo KernHawaii County Planning Department101 Pauahi Street, Ste. 3Hilo, HI 96720 SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES Dear Mr. Kern: Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV)hereby submits the Weekly Status Report for the week ending July 2, 2023. Power plantPlant in service. Wellfield KS-22, continued drilling, current depth is 6900’. If you have any questions, please do not… Read More »Weekly Updates – July 3, 2023

weekly update

Weekly Updates – June 26, 2023

  • by

June 26, 2023 Zendo KernHawaii County Planning Department101 Pauahi Street, Ste. 3Hilo, HI 96720 SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES Dear Mr. Kern: Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV)hereby submits the Weekly Status Report for the week ending June 25, 2023. Power plantPlant in service. Wellfield KS-22, continued drilling, current depth is 6012’. If you have any questions, please do not… Read More »Weekly Updates – June 26, 2023

weekly update

Weekly Updates – June 19, 2023

  • by

June 19, 2023 Zendo KernHawaii County Planning Department101 Pauahi Street, Ste. 3Hilo, HI 96720 SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES Dear Mr. Kern: Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV)hereby submits the Weekly Status Report for the week ending June 18, 2023. Power plantPlant in service. Wellfield KS-22, continued drilling, current depth is 5306’. If you have any questions, please do not… Read More »Weekly Updates – June 19, 2023

weekly update

Weekly Updates – June 12, 2023

  • by

June 12, 2023 Zendo KernHawaii County Planning Department101 Pauahi Street, Ste. 3Hilo, HI 96720 SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES Dear Mr. Kern: Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV)hereby submits the Weekly Status Report for the week ending June 11, 2023. Power plantPlant in service. Wellfield KS-22, continued drilling, current depth is 4908’. If you have any questions, please do not… Read More »Weekly Updates – June 12, 2023

weekly update

Weekly Updates – June 6, 2023

  • by

June 6, 2023 Zendo KernHawaii County Planning Department101 Pauahi Street, Ste. 3Hilo, HI 96720 SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES Dear Mr. Kern: Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV)hereby submits the Weekly Status Report for the week ending June 4, 2023. Power plantPlant in service. Wellfield KS-22, continued drilling, current depth is 3962’. If you have any questions, please do not… Read More »Weekly Updates – June 6, 2023