Weekly Updates – May 30, 2023

  • by

May 30, 2023 Zendo KernHawaii County Planning Department101 Pauahi Street, Ste. 3Hilo, HI 96720 SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES Dear Mr. Kern: Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV)hereby submits the Weekly Status Report for the week ending May 28, 2023. Power plantPlant in service. Wellfield KS-22, well casing installed, recommenced drilling, current depth is 3229’. If you have any questions,… Read More »Weekly Updates – May 30, 2023

weekly update

Weekly Updates – May 22, 2023

  • by

May 22, 2023 Zendo KernHawaii County Planning Department101 Pauahi Street, Ste. 3Hilo, HI 96720 SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES Dear Mr. Kern: Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV)hereby submits the Weekly Status Report for the week ending May 21, 2023. Power plantPlant in service. Wellfield KS-22, continued underreaming in preparation to install well casing. Continued performing well testing on KS-21… Read More »Weekly Updates – May 22, 2023

weekly update

Weekly Updates – May 15, 2023

  • by

May 15, 2023 Zendo KernHawaii County Planning Department101 Pauahi Street, Ste. 3Hilo, HI 96720 SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES Dear Mr. Kern: Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV)hereby submits the Weekly Status Report for the week ending May 14, 2023. Power plantPlant in service. Wellfield KS-22, underreaming commenced in preparation to install well casing. Continued performing well testing on KS-21… Read More »Weekly Updates – May 15, 2023

weekly update

Weekly Updates – May 9, 2023

  • by

May 9, 2023 Zendo KernHawaii County Planning Department101 Pauahi Street, Ste. 3Hilo, HI 96720 SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES Dear Mr. Kern: Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV)hereby submits the Weekly Status Report for the week ending May 7, 2023. Power plantPlant in service. Wellfield Continued drilling KS-22, currently depth is 2935’. Continued injection testing into KS-21. If you have… Read More »Weekly Updates – May 9, 2023

weekly update

Weekly Updates – May 1, 2023

  • by

May 1, 2023 Zendo KernHawaii County Planning Department101 Pauahi Street, Ste. 3Hilo, HI 96720 SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES Dear Mr. Kern: Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV)hereby submits the Weekly Status Report for the week ending April 30, 2023. Power plantPlant in service. Wellfield Continued drilling KS-22, currently depth is 1770’ Continued injection testing into KS-21. If you have… Read More »Weekly Updates – May 1, 2023

weekly update

Weekly Updates – April 24, 2023

  • by

April 24, 2023 Zendo KernHawaii County Planning Department101 Pauahi Street, Ste. 3Hilo, HI 96720 SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES Dear Mr. Kern: Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV)hereby submits the Weekly Status Report for the week ending April 23, 2023. Power plantPlant in service. Wellfield Continued drilling KS-22, currently depth is 1234’ Commenced injection testing into KS-21. If you have… Read More »Weekly Updates – April 24, 2023

weekly update

Weekly Updates – April 17, 2023

  • by

April 17, 2023 Zendo KernHawaii County Planning Department101 Pauahi Street, Ste. 3Hilo, HI 96720 SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES Dear Mr. Kern: Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV)hereby submits the Weekly Status Report for the week ending April 16, 2023. Power plantPlant in service. Wellfield Continued drilling KS-22, currently depth is 1018’ Completed a successful flow test on KS-19. If… Read More »Weekly Updates – April 17, 2023

weekly update

Weekly Updates – April 10, 2023

  • by

April 10, 2023 Zendo KernHawaii County Planning Department101 Pauahi Street, Ste. 3Hilo, HI 96720 SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES Dear Mr. Kern: Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV)hereby submits the Weekly Status Report for the week ending April 9, 2023. Power plantPlant in service. Wellfield Continued drilling KS-22, currently depth is 760’ Continued preparations to flow test KS-19, the tentative… Read More »Weekly Updates – April 10, 2023

weekly update

Weekly Updates – April 6, 2023

  • by

April 6, 2023 Zendo KernHawaii County Planning Department101 Pauahi Street, Ste. 3Hilo, HI 96720 SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES Dear Mr. Kern: Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV)hereby submits the Weekly Status Report for the week ending April 2, 2023. Power plantPlant in service. Wellfield Continued drilling KS-22, currently depth is 740’. Continued preparations to flow test KS-19, the tentative… Read More »Weekly Updates – April 6, 2023

weekly update

Weekly Updates – March 28, 2023

  • by

March 28, 2023 Zendo KernHawaii County Planning Department101 Pauahi Street, Ste. 3Hilo, HI 96720 SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES Dear Mr. Kern: Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV)hereby submits the Weekly Status Report for the week ending March 26, 2023. Power plantPlant in service. Wellfield Commenced drilling KS-22. Completed Plug and Abandonment (P&A) of KS-1A injection well. If you have… Read More »Weekly Updates – March 28, 2023