March 21, 2022 Zendo KernHawaii County Planning Department101 Pauahi Street, Ste. 3Hilo, HI 96720 SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES Dear Mr. Kern: Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV)hereby submits the Weekly Status Report for the week ending March 20, 2022. Power plantIn service. Wellfield Continued preparations to recommence the drilling of KS-19. If you have any questions, please do not… Read More »Weekly Updates – March 21, 2022

weekly update

Weekly Updates – March 14, 2022

  • by

March 14, 2022 Zendo KernHawaii County Planning Department101 Pauahi Street, Ste. 3Hilo, HI 96720 SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES Dear Mr. Kern: Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV)hereby submits the Weekly Status Report for the week ending March 13, 2022. Power plantIn service. Wellfield Continued preparations to recommence the drilling of KS-19. If you have any questions, please do not… Read More »Weekly Updates – March 14, 2022

weekly update

Weekly Updates – March 7, 2022

  • by

March 7, 2022 Zendo KernHawaii County Planning Department101 Pauahi Street, Ste. 3Hilo, HI 96720 SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES Dear Mr. Kern: Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV)hereby submits the Weekly Status Report for the week ending March 6, 2022. Power plantCompleted our scheduled plant outage, restated the power plant. Wellfield Moving drill rig equipment to the KS-19 location in… Read More »Weekly Updates – March 7, 2022

weekly update

Weekly Updates – February 28, 2022

  • by

February 28, 2022 Zendo KernHawaii County Planning Department101 Pauahi Street, Ste. 3Hilo, HI 96720 SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES Dear Mr. Kern: Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV)hereby submits the Weekly Status Report for the week ending February 27, 2022. Power plantThe power plant is in operation. Wellfield Completed KS-5 mechanical integrity inspections, secured master valves and riggingdown Rig 4.… Read More »Weekly Updates – February 28, 2022

weekly update

Weekly Updates – February 24, 2022

  • by

February 23, 2022 Zendo KernHawaii County Planning Department101 Pauahi Street, Ste. 3Hilo, HI 96720 SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES Dear Mr. Kern: Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV)hereby submits the Weekly Status Report for the week ending February 23, 2022. Power plantThe power plant is in operation. Wellfield Continued KS-5 wellbore cleaning and mechanical integrity inspections. If you have any… Read More »Weekly Updates – February 24, 2022

weekly update

Weekly Updates – February 14, 2022

  • by

February 15, 2022 Zendo KernHawaii County Planning Department101 Pauahi Street, Ste. 3Hilo, HI 96720 SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES Dear Mr. Kern: Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV)hereby submits the Weekly Status Report for the week ending February 14, 2022. Power plantThe power plant is in operation. Wellfield Continued KS-5 wellbore cleaning and mechanical integrity inspections to a depth of5,874’… Read More »Weekly Updates – February 14, 2022

weekly update

Weekly Updates – February 8, 2022

  • by

February 8, 2022 Zendo KernHawaii County Planning Department101 Pauahi Street, Ste. 3Hilo, HI 96720 SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES Dear Mr. Kern: Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV)hereby submits the Weekly Status Report for the week ending February 7, 2022. Power plantThe power plant is in operation. WellfieldContinued KS-5 mechanical integrity inspections. If you have any questions, please do not… Read More »Weekly Updates – February 8, 2022

weekly update

Weekly Updates – February 1, 2022

  • by

February 1, 2022 Zendo KernHawaii County Planning Department101 Pauahi Street, Ste. 3Hilo, HI 96720 SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES Dear Mr. Kern: Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV)hereby submits the Weekly Status Report for the week ending January 30, 2022. Power plantThe power plant is in operation. WellfieldContinued KS-5 mechanical integrity inspections. If you have any questions, please do not… Read More »Weekly Updates – February 1, 2022

weekly update

Weekly Updates – January 24, 2022

  • by

January 24, 2022 Zendo KernHawaii County Planning Department101 Pauahi Street, Ste. 3Hilo, HI 96720 SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES Dear Mr. Kern: Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV)hereby submits the Weekly Status Report for the week ending January 23, 2022. Power plantThe power plant is in operation. WellfieldContinued KS-5 mechanical integrity inspections. If you have any questions, please do not… Read More »Weekly Updates – January 24, 2022

weekly update

Weekly Updates – January 17, 2022

  • by

January 17, 2022 Zendo KernHawaii County Planning Department101 Pauahi Street, Ste. 3Hilo, HI 96720 SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES Dear Mr. Kern: Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV)hereby submits the Weekly Status Report for the week ending January 16, 2022. Power plantThe power plant is in operation. WellfieldContinued KS-5 mechanical integrity inspections. If you have any questions, please do not… Read More »Weekly Updates – January 17, 2022