Weekly Update: December 29, 2019

  • by
weekly update

December 29, 2019

Michael Yee
Hawaii County Planning Department
101 Pauahi Street, Ste. 3
Hilo, HI 96720

SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES

Dear Mr. Yee:
Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture(PGV) hereby submits the Weekly Status Report for the week ending December 30, 2019.

Power plant

  • Continued with turbine and generator overhauls.
  • OEC 25 continued power skid equipment installation.
  • Waiting on building permits to continue substation installation.
  • Making preparations to export test energy though our electrical service connection.

Wellfield

  • KS-13 Completed cleanout with Rig 1, moving drill rig to KS-18.
  • KS-14 Continued preparations to flow the well to process.
  • KS-18 Staging equipment to recommence drilling with Rig 1.
  • MW-5 Continued drilling monitoring well.

If you have any questions, please do not hesitate to call me.

Sincerely,

Ronald P. Quesada
EH&S Manager