SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES

Dear Mr. Yee:

Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV) hereby submits the Weekly Status Report for the week ending January 19, 2020.

Power plant
Continued with turbine and generator overhauls.

  • OEC 11 continued power skid equipment installation.
  • OEC 22 continued power skid equipment installation.
  • OEC 25 continued power skid equipment installation.

Waiting on building permits to continue substation installation.

Wellfield

  • KS-13 Continued with reinstalling surface equipment.
  • KS-14 Well maintenance will continue when Rig 4 is available.
  • KS-18 Continued drilling with Rig 1.
  • MW-5 Continued drilling monitoring well with Rig 4.