Skip to content

Weekly Update: January 6, 2020

  • by
weekly update

January 6, 2020
Michael Yee
Hawaii County Planning Department
101 Pauahi Street, Ste. 3
Hilo, HI 96720

SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES

Dear Mr. Yee:

Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture(PGV) hereby submits the Weekly Status Report for the week ending January 5, 2020.

Power plant
Continued with turbine and generator overhauls.

  • OEC 11 commenced power skid equipment installation.
  • OEC 22 commenced power skid equipment installation.
  • OEC 25 continued power skid equipment installation

Waiting on building permits to continue substation installation.

Wellfield

  • KS-13 Reinstalling surface equipment.
  • KS-14 Upon further testing, well maintenance will continue when Rig 4 is available.
  • KS-18 Continued staging equipment to recommence drilling with Rig 1.
  • MW-5 Continued drilling monitoring well with Rig 4.

If you have any questions, please do not hesitate to call me.

Sincerely,

Ronald P. Quesada
EH&S Manager