April 6, 2020
Michael Yee
Hawaii County Planning Department
101 Pauahi Street, Ste. 3
Hilo, HI 96720
SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES
Dear Mr. Yee:
Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV) hereby submits the Weekly Status Report for the week ending March 22, 2020.
Power plant
Continued with turbine and generator overhauls.
- OEC 11 continued power skid equipment installation.
- OEC 22 continued power skid equipment installation.
- OEC 25 continued power skid equipment installation.
Continued electrical substation installation.
Wellfield
- KS-14 Well maintenance will continue when Rig 4 is available.
- KS-17 Conductor installed, continued waiting on cement to finalize installation
- KS-18 Drilling will continue once MW-4 pump operational testing is complete.
- MW-5 Drilling postponed, relocated Rig #4 to KS-17.
- MW-4 Pump repaired, performing operational testing
If you have any questions, please do not hesitate to call me.
Sincerely,
Ronald P. Quesada
EH&S Manager