Skip to content

Weekly Updates – August 3, 2020

weekly update

August 3, 2020

Michael Yee
Hawaii County Planning Department
101 Pauahi Street, Ste. 3
Hilo, HI 96720

SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES

Dear Mr. Yee:

Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV) hereby submits the Weekly Status Report for the week ending August 2, 2020.

Power plant

  • OEC 22 continued final system checks. Electrical substation is complete mechanically, preparing to perform electrical function testing.

Wellfield

  • KS-14 Reevaluating well maintenance
  • KS-17 Current depth is 2,282’, prepared to perform cementing integrity testing (cement bond log).
  • KS-18 Commenced well maintenance.
  • MW-5 Drilling postponed.
  • MW-4 Pump is in operation.

If you have any questions, please do not hesitate to call me.

Sincerely,

Ronald P. Quesada
EH&S Manager