Weekly Updates – March 22, 2021

weekly update

March 22, 2021

Zendo Kern
Hawaii County Planning Department
101 Pauahi Street, Ste. 3
Hilo, HI 96720

SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES

Dear Mr. Kern:

Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV) hereby submits the Weekly Status Report for the week ending March 21, 2021.

Power plant

The power plant is in operation.

Wellfield

  • KS-11 Removed damaged casing, continued clean out. 
  • KS-14 In service.
  • KS-17 In service.
  • KS-18 In service.
  • KS-19 Waiting for drill rig availability
  • KS-20 Reamed and cleaned hole to 7,038’ in preparation to install well casing. 
  • MW-5 Drilling postponed.
  • MW-4 In service.

If you have any questions, please do not hesitate to call me.

Sincerely,

Ronald P. Quesada
EH&S Manager