Skip to content

Weekly Updates – October 17, 2022

  • by
weekly update

October 17, 2022

Zendo Kern
Hawaii County Planning Department
101 Pauahi Street, Ste. 3
Hilo, HI 96720

SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES

Dear Mr. Kern:

Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV)
hereby submits the Weekly Status Report for the week ending October 16, 2022.

Power plant
In service.

Wellfield

Performed drill rig equipment inspections at KS-21 location.

If you have any questions, please do not hesitate to call me at (808) 430-8679.

Sincerely,

Ronald P. Quesada
EH&S Manager