SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES

Dear Mr. Yee:

Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV) hereby submits the Weekly Status Report for the week ending October 18, 2020.

Power plant

  • Continued function testing in electrical substation.

Wellfield

  • KS-14 Well maintenance delayed.
  • KS-17 Continued installing wellhead equipment.
  • KS-18 Continued well maintenance.
  • MW-5 Drilling postponed.
  • MW-4 Pump is in operation.

If you have any questions, please do not hesitate to call me.

Sincerely,

Ronald P. Quesada
EH&S Manager