Weekly Updates – September 7, 2020

weekly update

September 8, 2020

Michael Yee
Hawaii County Planning Department
101 Pauahi Street, Ste. 3
Hilo, HI 96720

SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES

Dear Mr. Yee:

Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV) hereby submits the Weekly Status Report for the week ending September 7, 2020.

Power plant

  • Continued preparation to perform substation electrical function testing.

Wellfield

  • KS-14 Reevaluating well maintenance
  • KS-17 Continue drilling, current depth is 4,753’.
  • KS-18 Continued well casing maintenance.
  • MW-5 Drilling postponed.
  • MW-4 Pump is in operation.

If you have any questions, please do not hesitate to call me.

Sincerely,

Ronald P. Quesada
EH&S Manager